March 15, 2010 at March 15, 2010 · Filed under enart.nnxj.comedit
I have inherited some code that needs some updates. Users create MS
Project files and upload them from a website into an Oracle database
using ASP and VBScript. Users may then view the MS Project file via
the web. The MS Project file info is parsed into the Oracle database
and then retrieved for presentation on the Web. The user has
correctly set the calendar to Fiscal Years beginning 1-October. The
Project files all display according to Fiscal Year and Quarter.
However, when the info is parsed and displayed on the Web the Fiscal
Year is shown as starting on 1-January, thus incorrectly displaying
task start and stop dates. I already know that the calendar setting
in the .mpp file is correct. What I need to know is how to make sure
the web version of the Project File displays Fiscal Years/Quarters
that start 1-October.
#If you have any other info about this subject , Please add it free.# |
|